ComEd successfully energized two new 345 kV transmission substations in Illinois, enabling interconnection of up to 550 MW of wind generation from two utility-scale wind farms (Osagrove Flats 150 MW, Panther Grove 400 MW) expected online in late 2026 and early 2027—capacity equivalent to serving approximately 264,000 homes annually.
Goodlede runs a two-pass source check on every story: one pass finds it, a second skeptical pass re-verifies the claim and writes what it doesn’t prove. This is a source check, not an independent fact-check — confirm anything important at the link above.
Read the full story at CleanTechnica
Read original story ↗More good news, verified daily.
Goodlede covers positive developments across science, nature, rights, and human achievement — verified before they appear. No hype, no roundups, no PR wires.
© 2026 Wag Media, LLC
More from Goodlede
Kindness
A Streetside Painting Salvaged for its Frame Returned After Honest Man Realized its Enormous Value
Good News Network · Verified
Science
A Human Habitat at The Bottom of The Ocean Is Now Operational. Take a Look Inside
ScienceAlert · Verified
Environment
India: Delhi adds 300 electric buses to its public transport fleet
Electrive · Verified